Lee’s Summit High School is the most extensive project on LSR7’s docket.

The Facts

 

$80M

Total Budget

January 2021

Start Date

August 2023

Completion Date

MultiStudio

Architect

 
 

 
 

Demolish.

Demolish the 1952 classrooms located along the southern exterior of the building and create a new southern facade.

Renovate.

Renovate the western exterior of LSHS and provide a new western entrance near the current administrative offices.

Add.

Add 60,000 square feet of new construction, including a wide two-story “heart” or “spine” connecting Buildings A, B and C.

 

Locate.

Locate a new, centralized media center in this central connecting building, as well as future-ready, collaboration and innovative learning environments

Provide.

Provide light to heavy interior renovations for nearly all instructional and public spaces

Project Updates

March 2023

With spring break came a new library and classrooms in the additions for the students and staff at Lee’s Summit High School.

 

February 2023

Finishes were installed in Zone G old administration area and the new topping slab was poured in the North addition - paving a pathway to the new media center.

 

January 2023

In January, new renovation areas started in Zone G3 and H2 restroom, and the additions continued on with the exterior facade and overhead mechanical and electrical systems.

 

December 2022

Another renovation area was wrapped up to prepare for students and staff to start the Spring 2023 semester. The additions continued forward with skin, roofing, and overhead electrical, mechanical and plumbing.

 

November 2022

Walls and ceilings were hung to start creating the classrooms in the B Building renovation, while the South addition started taking shape with its new steel structure.

 

October 2022

Mechanical, electrical and plumbing work was in full swing throughout the renovations, as the North addition received skin.

 

September 2022

A new renovation area in the East wings of B Building kicked off. The second phases of the Addition on the North and South were in full swing - including structural steel and new concrete foundations.

 

August 2022

Final touches wrapped up and teachers moved into their new and improved classrooms for the start of Fall 2022 semester.

 

July 2022

Renovations continued in the art and life skills’ wings. Drywall was hung and finished, paint started, and lights illuminated.

 

June 2022

Addition 2 demolition and underground utilities continued through June in preparation for structural footings and steel. Demolition and new MEP system install was in full swing in the renovation spaces.

 

May 2022

Addition 1 interior finishes and new roofing wrapped up, and staff moved in to their new administration offices.

Staff moved out and demolition crews moved in to our new renovation spaces following the Memorial Day holiday.

 

April 2022

Topping slabs were poured in the addition clerestory, and new wood baffle ceilings and wood panel walls continued. Overhead MEP, metal studs and drywall continued in the renovation space in B Building.

 

March 2022

At the addition, paint and finishes continued to be installed in preparation for move in following the end of the school year.

In the renovation, key mechanical, plumbing, electrical, and sprinkler systems were installed.

 

February 2022

Drywall finishing, installation of permanent lighting and electrical devices continued in the addition, while new mechanical systems were installed in the renovation in February of 2022.

 

January 2022

After completing renovation of the science wing, construction moved to the new teacher collaboration and classrooms in B Building. Demolition began in January to kick off the start of the new year.

 

December 2021

In the renovation, the final science wing and the modern language wing were completed for students to return following the winter break.

At the additional, huge progress was made with overhead and in-wall MEP systems.

 

November 2021

At the addition, interior wall framing, door frames, and a roofing system were installed. Simultaneously in the renovation, a new brick façade was started on the North face of A Building and the interior finishes pursued.

 

October 2021

Renovations to the Science and Modern Language wings pursued, as the Addition enclosure continued with wall framing and exterior gypsum board starting.

 
20210921_143417021_iOS.jpg

September 2021

Structural steel wrapped up and exterior wall framing began at the Addition, while another renovation ramped up in the remaining science wing.

 
20210823_174233736_iOS.jpg

Summer 2021 Wrap Up

Students and staff returned to scho0l to newly renovated spaces and the new addition continued forward with structure steel starting.

 
20210823_175304808_iOS.jpg

August 2021

New acoustical ceilings, updated LED lights, and fresh flooring and paint wrap up the summer 2021 renovations areas in August.

 

July 2021

Classrooms started developing in July as drywall enclosed the science and math wings.

 

June 2021

June involved the installation of critical overhead systems and new masonry walls .

 
 
Screen Shot 2021-06-14 at 12.13.27 PM.png

May 2021

May became a productive month with metal framing and roughing in of mechanical, electrical and plumbing.

 
Screen Shot 2021-06-14 at 12.07.07 PM.png

April 2021

Wrapping up demo in Area J and building temporary walls highlights the inaugural month of construction at Lee’s Summit High School.

 